Tuesday, August 21, 2007
Poland excluded from joint nuclear plant project?
Poland excluded from joint nuclear plant project?
Created: Tuesday, August 21. 2007
Poland’s place in a project constructing a new nuclear power plant in Lithuania might be taken by one of the Western countries, Lithuanian "Verslo żinios" business daily informs, quoting some anonymous sources of state institutions.
The newspaper reminds that the Poles are constantly unsatisfied with the division of shares of the planned power station. Lack of agreement on this matter delays the date of starting the construction.
According to an act of Lithuanian Parliament, Lithuania is to take 34 percent of the shares, and Poland, Latvia and Estonia 22 percent each. This division caused Polish hesitation whether to take part in the project or not.
The new nuclear power plant is to start operating in 2015. It is to take over the old one, still remembering soviet times, in Ignalin, which Lithuania agreed to close by the end of 2010, The planned power of the plant is to amount to 3.400 MW. This is by 200 MW less then originally planned. The project has been changed after Poland threatened to withdraw from the investment if the country does not receive 1/3 of the produced energy.
Friday, August 10, 2007
Polska Grupa Energetyczna w przyszłym roku planuje swój debiut
Energetyka chce na giełdę
Nasz Dziennik, 2007-08-10
Polska Grupa Energetyczna w przyszłym roku planuje swój debiut na Giełdzie Papierów Wartościowych w Warszawie. Planowana jest emisja do 35 proc. akcji grupy. Obecnie po zakończeniu konsolidacji przez włączenie PGE Energia SA, BOT Górnictwo i Energetyki SA grupa opracowuje strategię działania. PGE zapowiada też, że jeszcze w tym roku wprowadzi równą stawkę dla wszystkich swoich klientów indywidualnych.
- Po pozytywnie zakończonym w maju 2007 roku procesie konsolidacji rozpoczynamy II etap procesu budowy Polskiej Grupy Energetycznej, który wzmocni wartość PGE i przygotuje grupę do debiutu giełdowego w przyszłym roku - stwierdził Paweł Urbański, prezes zarządu Polskich Sieci Energetycznych.
Konsolidacja firm sektora elektroenergetycznego następuje w ramach rządowego "Programu dla elektroenergetyki". Według programu właśnie podmiot o znacznej sile ma być zdolny do realizacji kluczowych inwestycji na obszarze kraju oraz do aktywnego włączenia się w działalność na europejskim rynku energii. W ramach tego procesu została utworzona Polska Grupa Energetyczna, w skład której oprócz Polskich Sieci Elektroenergetycznych weszły dwa podmioty wytwarzające energię elektryczną: BOT Górnictwo i Energetyka SA (dwie kopalnie i trzy elektrownie) oraz Zespół Elektrowni Dolna Odra. Natomiast dystrybucją energii zajmuje się osiem spółek.
W ocenie wiceprezesa PSE Emila Wojtowicza, holding po połączeniu ma większe możliwości ograniczenia kosztów działania. W 2008 r. wydatki PGE mają wynieść 15,5 mld złotych. Grupa chce w ciągu 3-4 lat zmniejszyć je o 1 mld złotych.
Do 2025 roku PGE planuje zwiększyć moce wytwórcze o 10 tys. MW energii elektrycznej. Obecnie grupa wytwarza łącznie ponad 11 tys. MW. Według PSE, w 2030 roku Polska będzie potrzebować 20-25 tys. MW nowych mocy energii elektrycznej. Zapotrzebowanie na energię w Polsce rośnie w granicach 5-6 proc. rocznie, a ponad 40 proc. krajowych elektrowni przekroczyło 30 lat i wymaga modernizacji. Zdaniem Urbańskiego, w 2021 r. Polska powinna uruchomić pierwszy blok elektrowni atomowej o mocy 1600 MW. Pod znakiem zapytania stoi udział naszego kraju w elektrowni atomowej w Ignalinie na Litwie. - Gdy bilansujemy potrzeby krajów biorących udział w tym projekcie, nie mamy wątpliwości, że moc tej elektrowni musi wynieść powyżej 3 tys. MW - uważa Urbański. Jednak określenie mocy elektrowni będzie zależeć od prowadzonych badań środowiskowych i geologicznych. Jeśli okazałoby się, że moc elektrowni z tych względów musi być ograniczona, to nie wiadomo, czy Polska będzie uczestniczyć w tym projekcie.
Grzegorz Lipka
Poland reiterates interest in new Lithuanian nuclear power plant
Poland reiterates interest in new Lithuanian nuclear power plant, but only at high capacities 17:26 09.08.2007
czwartek
Participants of the new nuclear power plant project in Lithuania approved the power plant's projected capacity at above 3,000 MW, although the final capacity will depend on the evaluation of environmental impact of the project and Poland is reiterating its interest only in a large-scale project, said Pawel Urbanski, the president of Polish power grid operator Polskie Sieci Elektroenergetyczne (PSE).
"The parties agreed to the option of more than 3,000 MW, though discussions continue," Urbanski told a press conference Thursday. "The work on the evaluation of the environmental impact needs to be done first. [...] We're interested only in a large project."
According to a Lithuanian bill on the new power plant that is supposed to replace the existing Ignalina plant, the new facility will have capacity of 1,600-3,200 MW. Latvia and Estonia have already declared an interest in the project, but Polish Economy Minister Piotr Wozniak said earlier Poland will not take part in the project if it is not guaranteed to get 1,200-1,600 MW of energy from the plant.
PSE's vice-president Henryk Baranowski said Thursday the work on the environmental impact of the new power plant is going on, with the evaluation supposed to be ready by the end of the first half of 2008.
"It will later be the subject of consultations and should be approved by the end of 2008," Baranowski said
czwartek
Participants of the new nuclear power plant project in Lithuania approved the power plant's projected capacity at above 3,000 MW, although the final capacity will depend on the evaluation of environmental impact of the project and Poland is reiterating its interest only in a large-scale project, said Pawel Urbanski, the president of Polish power grid operator Polskie Sieci Elektroenergetyczne (PSE).
"The parties agreed to the option of more than 3,000 MW, though discussions continue," Urbanski told a press conference Thursday. "The work on the evaluation of the environmental impact needs to be done first. [...] We're interested only in a large project."
According to a Lithuanian bill on the new power plant that is supposed to replace the existing Ignalina plant, the new facility will have capacity of 1,600-3,200 MW. Latvia and Estonia have already declared an interest in the project, but Polish Economy Minister Piotr Wozniak said earlier Poland will not take part in the project if it is not guaranteed to get 1,200-1,600 MW of energy from the plant.
PSE's vice-president Henryk Baranowski said Thursday the work on the environmental impact of the new power plant is going on, with the evaluation supposed to be ready by the end of the first half of 2008.
"It will later be the subject of consultations and should be approved by the end of 2008," Baranowski said
Subscribe to:
Posts (Atom)